22/04/2026

[PROJECT UPDATE] RAICO VIETNAM FACTORY – A MODERN LEED GOLD STANDARD PROJECT TAKING SHAPE

The Raico Vietnam Manufacturing Plant is entering its final phase, with clear progress visible on-site. Key project components are being implemented simultaneously, closely following the planned schedule and technical requirements.

HGPT Steel is responsible for the fabrication and installation of steel structures for the Raico Vietnam factory

The expanded workshop area has nearly completed its final stages—from steel erection to finishing details—and is now ready for handover on schedule. This is one of the representative projects showcasing HGPT’s capability in executing large-scale industrial steel structure projects in Da Nang.

Meanwhile, the warehouse section is progressing steadily, reaching approximately 30% completion. The construction team is focusing resources to ensure continuous and synchronized execution, while strictly controlling technical and safety standards—key factors in steel structure construction projects today.

Thanks to close collaboration between HGPT Steel and the investor, the project is steadily taking shape day by day. Each precisely installed steel component contributes to the overall structure, ensuring the project develops in a synchronized and sustainable manner. This also serves as strong proof of the quality and reliability of steel structure contractors in Da Nang, particularly in FDI projects.

Raico Vietnam – A LEED Gold Certified Factory

Beyond meeting schedule requirements, the Raico Vietnam project is oriented toward becoming a modern LEED Gold-certified factory—an international standard for green buildings. The project is optimized for operational efficiency, energy savings, and environmental impact reduction, aligning with the sustainable development trend in the steel structure and construction industry.

Project Information:
– Project: Hoa Vang Logistics Center – Da Nang Port
– Scope of Work: Supply of steel structures for Warehouse No. 02 & Warehouse No. 03
– Project Owner: Da Nang Port Joint Stock Company
– Steel Structure Contractor: HGPT STEEL

Contact information:

HA GIANG PHUOC TUONG MECHANICAL JSC (HGPT Steel)

– Address: 8th, Hoa Cam industrial zone, Cam Le ward, Danang Da Nang

– Hotline: 0949.386.113

– Mail: tender@hgpt.vn – Website: https://hgptsteel.com/

– Fanpage: https://www.facebook.com/HGPTMechanicalJSC

Subscribe to HGPT STEEL Newsletter

Get the latest updates on projects, products, and company activities from HGPT STEEL. Take a look

    Related news

    07/04/2026

    🏗 TRA KHUC 1 – GATE INSTALLATION BEGINS

    To ensure progress and meet the EPC contractor’s plan for commissioning and grid connection of the Tra Khuc 1 Hydropower Project, all fabrication works for the sluice gate steel structures are currently being expedited at Factory No. 1 and No. 2.

    Read this post

    23/03/2026

    CONTINUING THE TRUST, HGPT PARTNERS WITH KIM LONG MOTOR ON A USD 130 MILLION EV BATTERY MANUFACTURING PLANT

    The working atmosphere at HGPT STEEL’s factory has become vibrant in the early days of Q4, as the first steel trusses for Warehouses No. 02 and 03 under the Hoa Vang Logistics Center – Da Nang Port Project have officially entered the fabrication phase.

    Read this post

    10/02/2026

    COMPLETING ONE OF THE TALLEST STEEL STRUCTURE BUILDINGS AT THE HOA PHAT DUNG QUAT PROJECT

    HGPT Steel has officially completed the contract for the fabrication and erection of the steel structure for Block 3 – Lime Workshop at Hoa Phat Dung Quat. As one of the tallest steel structure buildings within the project, the 8-story steel workshop, with a total weight of over 1,100 tons, required a high level of precision in both fabrication and installation.

    Read this post

    06/02/2026

    HGPT STEEL KICKS OFF A PROMISING 2026 WITH AN FDI PROJECT

    Entering 2026, HGPT STEEL continues to affirm its position by launching an FDI project – the Freeze-Dried Coffee Factory at Becamex Binh Dinh Industrial Park. This milestone marks a significant achievement, demonstrating HGPT STEEL’s capability, credibility, and extensive experience in the manufacturing and erection of pre-engineered steel buildings.

    Read this post

    15/01/2026

    ACCELERATING THE COMPLETION OF STEEL STRUCTURE FABRICATION FOR SLUICE GATES TRA KHUC 1 HYDROPOWER PROJECT – QUANG NGAI

    To ensure progress and meet the EPC contractor’s plan for commissioning and grid connection of the Tra Khuc 1 Hydropower Project, all fabrication works for the sluice gate steel structures are currently being expedited at Factory No. 1 and No. 2.

    Read this post

    07/01/2026

    [PROJECT UPDATE] HOA VANG LOGISTICS CENTER DA NANG – WAREHOUSE NO. 02

    At the construction site of the Hoa Vang Logistics Center Project – Da Nang Port, the first steel structural components of Warehouse No. 02, fabricated by HGPT STEEL, are being transported, erected, and progressively completed in accordance with the approved schedule. Each work item reflects precision in fabrication, consistency in design, and professionalism in steel structure erection works.

    Read this post

    31/10/2025

    HGPT STEEL WELCOMES THE SAN DIEGO PORT DELEGATION (USA) FOR THE SECOND VISIT

    On October 30, 2025, HGPT STEEL was honored to welcome the San Diego Port delegation for their second visit and working session at our factory. During the meeting, both sides discussed import–export policies, logistics cooperation opportunities, and HGPT’s steel structure production and export capabilities.

    Read this post

    20/10/2025

    HGPT STEEL ADVANCES WITH ISO 3834 STANDARD

    On October 22–23, 2024, HGPT STEEL held a working session with the international certification and auditing organization BUREAU VERITAS VIETNAM to conduct an assessment and evaluation for the ISO 3834 certification.

    Read this post